Load Testing · Senior · Question 29 of 76

Before a breakpoint test, what must be agreed?

Show the answer

Correct answer: Stop criteria, a kill switch and who watches the system

Explanation

Pushing to failure can harm shared infrastructure. Define limits like "stop when error rate > 5% or p99 > 3 s", and have someone ready to abort.