Load Testing · Middle · Question 63 of 76

Why run a test at 120-150% of the expected peak?

Show the answer

Correct answer: To have headroom for growth, bad estimates and failover

Explanation

Peaks are estimates, and losing a node or zone moves its traffic to others. Headroom tells you how much margin you have.