Load Testing · Middle · Question 6 of 76
You need 100 RPS, and one iteration takes about 1.5 s. Roughly how many VUs must be available?
- 1About 67
- 2About 150
- 3About 100
Show the answer
Correct answer: About 150
Explanation
By Little's law, concurrency = rate × time = 100 × 1.5 = 150. Add headroom, because iterations get slower under load.