Load Testing · Middle · Question 44 of 76
Why tie load test targets to the SLO and error budget?
- 1Because the error budget sets the number of VUs
- 2So results show whether the service keeps its real promise
- 3Because SLOs are only valid and measured during load tests
Show the answer
Correct answer: So results show whether the service keeps its real promise
Explanation
If the SLO is 99.9% of requests under 300 ms, the test should check exactly that at peak load. Targets made up for the test don't connect to real risk.